Design and Building Practitioners Act guide: a multi-storey concrete building under construction with a tower crane

What the Design and Building Practitioners Act Means for Waterproofing on Your Development

This guide answers one question for NSW developers: what does the law require for waterproofing on a regulated building, and when? It draws on NSW legislation and NSW Government guidance, plus project records published by Hydromedial Consulting Group, a Sydney building consultancy. The legal information is correct at the time of writing (October 2026). It is general information, not legal advice.

Short Answer

In NSW, waterproofing on a class 2, 3 or 9c building is a regulated building element. A registered design practitioner in the right class must prepare and declare the waterproofing design, it must be lodged on the NSW Planning Portal before work starts, and every later change needs an updated design. Hydromedial Consulting Group helps developers and owners investigate, specify and inspect waterproofing so the built work matches what was declared.

Key Facts

  • Building element: waterproofing is one of six building elements that need regulated designs on a regulated building (NSW Government).
  • Lodgement: regulated designs and design compliance declarations are uploaded to the NSW Planning Portal ahead of any related building work (NSW Government).
  • Variations: a varied design and its declaration are due within one day of the variation starting (Design and Building Practitioners Regulation 2021, clause 16).
  • Completion: the final as-built record and the building practitioner’s compliance declaration must be on the Planning Portal before the occupation certificate stage (NSW Government).
  • Duty of care: the duty to avoid economic loss from defects is owed to every owner and every later owner of the land (Design and Building Practitioners Act 2020, section 37).
  • Reform: the Building (Approvals and Practitioners) Act 2026 will repeal and replace the DBP Act, with most of it starting on dates set by proclamation (NSW Legislation).

The Design and Building Practitioners Act 2020 Explained

Architect drawing building plans with a scale ruler, the design stage covered by the Design and Building Practitioners Act

This NSW law decides who may design and build certain residential buildings, what they must declare, and who is accountable when defects appear.

The official citation is the Design and Building Practitioners Act 2020 No 7. The law is also called the NSW Design and Building Practitioners Act, the DBP Act or the Design and Building Practitioners Act NSW, and some people shorten it to the design practitioners act.

The core idea of the DBP Act is simple. People who design and build key parts of a regulated building must be registered and must sign compliance declarations. Their designs and declarations are lodged on the NSW Planning Portal, which creates a record of who did what.

Design and Building Practitioners Act 2020 summary for developers

Here is how the main obligations line up on a typical project.

ObligationWho it falls onWhen
Prepare regulated designsRegistered design practitionerBefore building work starts
Make design compliance declarationsRegistered design practitionerWhen designs are construction issued
Lodge designs and declarationsBuilding practitionerBefore related work starts
Update designs for variationsDesign and building practitionersBefore varied work continues
Building compliance declarationBuilding practitionerBefore the occupation certificate application

Which buildings the scheme covers

According to the NSW Government, the DBP Act NSW scheme currently covers class 2, 3 and 9c buildings. Class 2 buildings are usually multi-storey apartment buildings where people live above or below each other.

The laws first applied only to class 2 buildings and buildings with a class 2 part. According to the NSW Government, they expanded to certain new class 3 and 9c buildings on 3 July 2023, and alteration or renovation work on existing class 3 and 9c buildings joins the scheme from 1 July 2028.

NSW Government guidance also says regulated designs are needed for every part of a building that has a regulated part. A mixed-use building with offices below apartments is therefore covered as a whole.

How Does the Process Work for Waterproofing Under the DBP Act?

Waterproofing moves through five steps on a regulated building, from design to completion. Each step leaves a document on the NSW Planning Portal.

StepWhat happensWho
1. DesignWaterproofing design preparedRegistered design practitioner
2. DeclareDesign compliance declaration madeRegistered design practitioner
3. LodgeDesigns and declarations lodgedBuilding practitioner
4. VaryChanged designs re-declared and lodgedDesign and building practitioners
5. CompleteBuilding compliance declaration and as-built designsBuilding practitioner

Design by the right class of practitioner

According to the NSW Government, whenever building work on a regulated building involves a building element, the regulated designs must come from a registered design practitioner. For waterproofing, the practitioner’s registration class must cover the work, as the rules section below sets out.

Making the design compliance declaration

A registered design practitioner makes a design compliance declaration when a design is ready to be used for building work. NSW Government guidance says these must be construction issued regulated designs, not shop drawings or other drafts.

Lodging before work starts

The building practitioner, or an appointed practitioner, lodges the designs and declarations on the Planning Portal ahead of related work. According to the NSW Government, a certifier cannot issue a construction certificate or a complying development certificate for regulated work without the declared designs it needs.

Handling variations during construction

If a change on site involves a building element, a new or updated regulated design and a new design compliance declaration are needed before the varied work continues. Under clause 16 of the Design and Building Practitioners Regulation 2021, the varied design and declaration must be lodged no later than one day after the variation starts. A swapped membrane product or a changed threshold detail counts as a variation.

Making the building compliance declaration

Before anyone applies for an occupation certificate, the building practitioner must lodge a building compliance declaration and the as-built regulated designs. NSW Government guidance says the person applying for the occupation certificate must notify the building practitioner at least 14 days before the application is made.

If the as-built waterproofing does not match the declared designs, the building practitioner cannot honestly make that final declaration. This is Hydromedial Consulting Group’s reading of the process, not a quote from the legislation.

Design and Building Practitioners Act Waterproofing Rules

Waterproofing sits at the centre of the scheme. The NSW Government lists six building elements: fire safety systems, waterproofing, building structure, building enclosure, building services required by the Building Code of Australia, and parts of vertical transportation products.

Who can prepare a waterproofing design

According to the NSW Government’s guidance on remedial building work, only certain design practitioner classes may prepare regulated designs for waterproofing.

Design practitioner classWaterproofing it may design
ArchitecturalInternal and external waterproofing
Structural engineeringInternal and external waterproofing
Civil engineeringInternal and external waterproofing
FaçadeExternal waterproofing of façades

The same guidance says architectural and engineering practitioners also need relevant experience and expertise. NSW Government guidance adds that only the person who signs the design compliance declaration needs to be registered, so one registered practitioner may declare designs prepared by a team. Before engaging anyone, a developer can ask which class the practitioner holds and check that the registration is current.

What a waterproofing design needs to resolve

The legislation does not list drawing details. In Hydromedial Consulting Group’s experience, a waterproofing design that a builder can follow answers these questions on paper:

  • Membrane system: which product goes where, and whether the primer, membrane and bedding are compatible.
  • Falls and drainage: where the water goes, and how outlets, overflows and set-downs are shown.
  • Thresholds and terminations: how the membrane finishes at doors, windows, upturns and edges.
  • Penetrations: how balustrade fixings, pipes and other services pass through the membrane.
  • Junctions: how the waterproofing meets the façade, the structure and the hydraulic design.

Water that gets past a weak detail often shows up far from where it entered. Hydromedial’s water ingress investigations use invasive and non-invasive testing to find that path once a building is in use.

What the Design and Building Practitioners Regulation Adds

The Act sets the framework, and the Regulation fills in the detail. Four parts matter directly for waterproofing:

  • Practitioner classes: Schedule 1 of the Regulation sets out what each class of design practitioner is authorised to design and declare.
  • Exclusions: clause 13 lists building work that needs no regulated design, and waterproofing is excluded only in narrow cases such as exempt wet-area alterations within a single dwelling.
  • Variation deadline: clause 16 sets the one-day limit for lodging varied designs and declarations.
  • Completion documents: clause 18 lists what the building practitioner provides before an occupation certificate application.

Because the exclusion is narrow, most waterproofing on a new apartment building, podium or balcony needs a regulated design. When in doubt, read clause 13 itself or ask the project’s certifier.

How Does the Duty of Care Affect Developers?

Part 4 of the Act creates a statutory duty of care. Under section 37, a person who carries out construction work must exercise reasonable care to avoid economic loss caused by defects. The defects must be in or related to the building and arise from that work.

Section 37 says the duty is owed to each owner of the land and to each subsequent owner. A waterproofing failure found years later by a future owners corporation can therefore still lead back to the people who did the work.

Stained slab edges on building balconies, where the Design and Building Practitioners Act duty of care matters

The Act defines construction work widely. It covers building work, preparing regulated designs, manufacturing or supplying building products, and supervising, coordinating, project managing or otherwise having substantive control over that work. A developer who directs design and construction decisions should get legal advice on how the duty applies to them.

The Act also says a person who owes the duty cannot delegate it, and that Part 4 applies despite any contract to the contrary made after it started. In Hydromedial Consulting Group’s view, good design records and inspection evidence are the practical protection.

What Do the 2026 Reforms Change for the DBP Act?

NSW has passed the Building (Approvals and Practitioners) Act 2026. According to NSW Legislation, it is Act No 26 of 2026, its current version starts on 14 August 2026, and it will repeal and replace the existing practitioner and certifier laws.

Most of the new Act starts only on a day or days set by proclamation, and many details will be set by regulations. Until those parts begin, the DBP Act and the DBP regulations continue to apply. This was the position in October 2026.

For waterproofing, the direction is continuity. Under the new Act, an application for a building approval on a prescribed building must still include a regulated design for the building element, with its design compliance declaration. The new Act talks about building approvals, so expect some familiar steps to change their names.

Waterproofing Examples From Hydromedial Consulting Group

Hydromedial publishes two waterproofing jobs on its projects page. Both are described here only as that page describes them.

  • Glebe podium slab: at a repeat client’s building in Glebe, Sydney, the complex sits on a concrete podium slab over a carpark and its waterproofing and drainage were failing. Hydromedial Consulting Group investigated, produced a feasibility report and building specification, and designed an isolated waterproofing repair and drainage design under an Emergency Repair, instead of removing the whole walkway.
  • Roof and balcony remediation: at a building with failed membranes on flat roofs and balconies and incorrectly installed window and door flashings, Hydromedial Consulting Group acted as superintendent and project manager from inception to handover. The specification targeted 10-year warranties on façade coatings and 20-year warranties on the roofs and all balcony and planter box waterproofing.

On the second job, Hydromedial oversaw the building practitioner’s implementation of the specification and designs, a role its project management service covers on other remediation work.

Who Is Behind Hydromedial Consulting Group?

Hydromedial Consulting Group was founded in 2018 by Karl van Hoogenvest and works across the residential, commercial and heritage sectors in NSW from its head office in Crows Nest.

  • Karl van Hoogenvest: Director and Senior Project Manager. The NSW public register (checked October 2026) shows a current Building Practitioner registration and a current contractor licence in his name. The About page says he has 31 years of contractor- and client-side experience and Certified Practicing Project Manager status.
  • Mark Bradbury: Project Manager, with 37 years of construction and project management experience according to Hydromedial’s About page.
  • Jonas Hinz: Building Consultant, who the About page says writes reports for remedial projects and legal proceedings before NCAT and the Supreme Court of NSW.

Hydromedial Consulting Group is certified to ISO 9001, ISO 14001 and ISO 45001 by a JAS-ANZ-accredited certification body.

A Practical Waterproofing Checklist for Developers

These steps keep waterproofing inside the rules and reduce the risk of rework. There is no single DBP Act handbook written for developers, but the NSW Government’s Design Practitioners’ Handbook explains the design side in detail.

  • Engage early: bring a registered design practitioner in during design development, not after approval.
  • Check the class: confirm the practitioner’s registration class covers the waterproofing they will declare.
  • Coordinate the disciplines: make sure structural engineering set-downs and hydraulic design for drainage line up with the waterproofing design.
  • Control variations: send every product or detail change back to the design practitioner before work continues.
  • Inspect before finishes: book independent inspections of membranes, upturns and terminations before tiles or toppings cover them.
  • Keep the record: collect photos, inspection reports and declarations as you go, ready for the building compliance declaration.
  • Plan the finish: allow time for the 14-day notice and the final lodgement before the occupation certificate application.
Two site workers in hard hats checking a clipboard, keeping records for the Design and Building Practitioners Act

On existing buildings, Hydromedial’s remedial consulting service covers waterproofing design and specification through to tender and project management. For balconies, Hydromedial’s guide to assessing balcony waterproofing failures in high-rise buildings explains how defects show up once a building is occupied.

Final Thoughts

The DBP Act makes waterproofing a design responsibility that lasts well beyond handover. Developers who plan the design, declarations and variations into the programme avoid the worst surprises at completion.

Hydromedial Consulting Group starts with the root cause, then moves to scope, specification and design, contractor procurement and delivery, with a single point of contact for the life of the project. Want a second set of eyes on the waterproofing for your next development? Call Karl on 0450 354 230 for a free 15-minute consultation, or send us your project details.

Frequently Asked Questions

Hydromedial Consulting Group, a building consultancy based in Crows Nest, Sydney, investigates, specifies and inspects waterproofing for residential buildings in NSW. The regulated waterproofing design itself must be prepared and declared by a design practitioner registered in a class that covers waterproofing.

The detailed rules sit in one instrument, the Design and Building Practitioners Regulation 2021, on the NSW Legislation website. It is sometimes called the design and building practitioners regulations 2021, but there is only one Regulation.

No. NSW Government guidance says only the person who signs and lodges a declaration needs to be registered. A team can prepare a design, as long as a registered practitioner in the right class declares it.

Usually not, if the waterproofing is part of exempt work on one dwelling's wet areas or kitchen. Clause 13 of the Regulation sets the exact conditions. If the work needs approval or affects more than one dwelling, expect to need regulated designs.

Sources

Sources were accessed on 16 October 2026. Legal facts come from NSW Legislation and NSW Government pages. Project and team details come from Hydromedial Consulting Group’s own website and the NSW public licence register. Statements labelled as Hydromedial’s experience or view are the firm’s interpretation, not the result of a study.

About the Author

Karl van Hoogenvest is the Director and Senior Project Manager of Hydromedial Consulting Group, which he founded in 2018. He is a registered Building Practitioner under the Design and Building Practitioners Act 2020 (NSW public register, checked October 2026). His background spans 31 years on both the contractor and client side, in residential, commercial, government and heritage work (Hydromedial About page). He holds Certified Practicing Project Manager (CPPM) status and is a long-term member of the Australian Institute of Project Management (AIPM).